Project Overview
HMR Contracting completed access track and waterway remediation works at a private forestry property on Whites Road, Little River. The project focused on tidying post-harvest access tracks, stabilising an old skid site, and remediating water races and waterways to improve site stability, drainage, and long-term usability.
Location: Whites Road, Little River, Canterbury
Client Type: Private forestry owner
Job Type: General excavation, access track remediation, waterway remediation
Client Challenge
Following forestry harvesting, the client needed access tracks tidied and waterways remediated to stabilise the site and improve long-term access and drainage.
What We Delivered
Tidied and reopened forestry access tracks
Remediated water races and watercourses
Contoured and stabilised an old skid site
Stacked and secured slash to prevent material slipping down the bank
Completed all works using our 15-tonne excavator
Left the site stable, functional, and ready for ongoing use
Why HMR Was Chosen
HMR was selected for its experience in forestry remediation and ability to handle earthworks efficiently in rural environments.
Outcome
Access tracks were restored, waterways stabilised, and the skid site safely contoured, leaving the property in a tidy and secure condition following harvest operations.